AQW 13861/11-15 Written question to the Minister for Regional Development
To ask the Minister for Regional Development why Translink estimates that a new train timetable will not be introduced until the end of 2012.
Asked by Stewart Dickson MLA on 5 September 2012
- Answered
- Written
- Priority
- Tabled
- 5 September 2012
- Answer due by
- 13 September 2012
- Answered
- 10 September 20125 days after tabling
- Department
- Department for Infrastructure
- Priority question
- Yes
Answer
Translink has advised that there are a number of elements involved in the introduction of a new timetable. Translink has indicated that all of these elements will be in place by the end of 2012.
Firstly the process requires meaningful consultation, which is on-going. Secondly relevant communications plans for both staff and customers need to be developed and implemented.
Thirdly all elements of the New Trains capital programme need to be finalised and tested and commissioned where appropriate. Apart from the delivery and testing of the new trains and the platform extension programme, construction of the new train stabling and maintenance facility at Adelaide must be completed. This latter project will also require requisite staff transfers to fully mobilise the new facility.Finally revised work patterns arising from the change in timetable will require Translink to carry out appropriate staff training, amend staff rosters and plan the full logistics of train scheduling and signaling required for operation of the new timetable.