AQW 15776/11-15 Written question to the Minister for Regional Development

To ask the Minister for Regional Development what progress has been made on NI Water's capital projects in East Antrim.

Asked by Stewart Dickson MLA on 17 October 2012

  • Answered
  • Written
Tabled
17 October 2012
Answer due by
1 November 2012
Answered
30 October 201213 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

I have been advised by Northern Ireland Water (NIW) that the planned expenditure within its Capital Works Programme for East Antrim Constituency area is as detailed in the table below.

PeriodExpenditure (£000s)
PC10 year 3 (2012/13)£3,629
PC13 year 1 (2013/14)£7,235
PC13 year 2 (2014/15)£27
Total£10,891

This will include expenditure on projects such as improvements to Killylane Watermain, Lough Mourne Zone Watermain, Carrickfergus Zone Watermain, upgrading Carrickfergus Wastewater Treatment Works and capital maintenance at Larne Wastewater Treatment Works.