AQW 37464/11-15 Written question to the Minister for Regional Development
To ask the Minister for Regional Development whether the plans for a cycleway, as part of the A2 Shore Road upgrade at Greenisland, have been altered during construction.
Asked by Stewart Dickson MLA on 14 October 2014
- Answered
- Written
- After due date
- Tabled
- 14 October 2014
- Answer due by
- 29 October 2014
- Answered
- 5 January 201583 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
The published plans for the A2 Shore Road Greenisland include a continuous combined footway/cycleway on the shore side of the road, between Jordanstown Road and Station Road Greenisland. These plans have not changed during construction.