AQW 45175/11-15 Written question to the Minister for Regional Development

To ask the Minister for Regional Development whether Translink has considered the cost of completely relaying track between York Street and Central Station; and if so, to provide details of the cost.

Asked by Stewart Dickson MLA on 28 April 2015

  • Answered
  • Written
Tabled
28 April 2015
Answer due by
14 May 2015
Answered
12 May 201514 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

Translink is currently engaging with my Department’s Transport NI York Street Interchange Project Team to coordinate the design and construction of essential enabling works to the Dargan Viaduct piers and foundations, in order to facilitate future dualling of the section between Yorkgate and Donegall Quay.

It is hoped to bring forward a Business Case in 2016/17 for these, enabling works to coincide with the York Street Interchange project schedule. The scheme will be dependent on funding availability within the next Comprehensive Spending Review period. As no Business case has been prepared yet, there are no cost details at this time.

There are no plans to relay the track this year or next.