AQW 5764/16-21 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure to detail the estimated cost of planning for the York Street Interchange since 2009.
Asked by Stewart Dickson MLA on 19 October 2016
- Answered
- Written
- Tabled
- 19 October 2016
- Answer due by
- 3 November 2016
- Answered
- 27 October 20168 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
I can confirm that the costs incurred in the development of the York Street Interchange Scheme since 2009 are as follows:
| Year | Expenditure (£) |
| 2009/10 | 399,640 |
| 2010/11 | 269,284 |
| 2011/12 | 602,684 |
| 2012/13 | 878,403 |
| 2013/14 | 850,468 |
| 2014/15 | 1,525,067 |
| 2015/16 | 1,836,931 |
| 2016/17 | 409,855 |
Please note that the expenditure for 2016/17 is to the end of September 2016.