AQW 2179/17-22 Written question to the Minister of Agriculture, Environment and Rural Affairs

To ask the Minister of Agriculture, Environment and Rural Affairs to outline the rationale for extending the Islandmagee Gas Storage Project Consultation.

Asked by Stewart Dickson MLA on 17 February 2020

  • Answered
  • Written
  • Priority
Tabled
17 February 2020
Answer due by
25 February 2020
Answered
25 February 20208 days after tabling
Department
Department of Agriculture, Environment and Rural Affairs
Priority question
Yes

Answer

The Department received a letter alleging shortcomings with the public notice advertising the consultation on the updated application, Environmental Statement and Marine Environmental Conditions Update Report for the proposed Islandmagee Gas Storage project.

Following a review of the notice, the Department decided to re-advertise and extend the consultation using an amended notice.

DAERA has contacted all respondents informing them of the revised consultation closing date of 27 March. Respondents have also been advised that while they do not have to make a further response, they can use this period to add any additional comments in support of their views.