AQW 5857/17-22 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure whether the dualling of the Dargan Viaduct will be prioritised as part of the future proofing of the York Street Interchange project.

Asked by Stewart Dickson MLA on 27 July 2020

  • Answered
  • Written
Tabled
27 July 2020
Answer due by
11 August 2020
Answered
10 August 202014 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

As part of the development of the York Street Interchange project, a feasibility study on the dualling of the Dargan Viaduct has been completed. It is proposed that works to strengthen the foundations and piers of the Dargan Viaduct will be delivered as part of the York Street Interchange as future proofing for further work.