AQW 9677/17-22 Written question to the Minister for the Economy
To ask the Minister for the Economy whether the unsuccessful bid for capital funding for Project Stratum in the October monitoring round will impact or delay the project.
Asked by Stewart Dickson MLA on 4 November 2020
- Answered
- Written
- Tabled
- 4 November 2020
- Answer due by
- 19 November 2020
- Answered
- 13 November 20209 days after tabling
- Department
- Department for the Economy
- Priority question
- No
Answer
There is no anticipated delay to Project Stratum as full project funding has been confirmed.