AQW 16422/17-22 Written question to the Minister of Agriculture, Environment and Rural Affairs

To ask the Minister of Agriculture, Environment and Rural Affairs pursuant to AQW 15709/17-22, (i) for an estimate of the costs to his Department associated with halting work; and (ii) what advice was sought prior to the decision to halt construction work.

Asked by Stewart Dickson MLA on 16 March 2021

  • Answered
  • Written
Tabled
16 March 2021
Answer due by
1 April 2021
Answered
30 March 202114 days after tabling
Department
Department of Agriculture, Environment and Rural Affairs
Priority question
No

Answer

On 26th February former Minister Lyons instructed DAERA officials to halt works in relation to the permanent infrastructure facilities at the Northern Ireland Points of Entry.

Construction of the permanent facilities has not yet commenced and my Officials will work through the contractual implications and associated costs of any decision to suspend construction work once the extent is realised.

I have previously confirmed that I will be bringing the matter to the Executive for consideration as soon as possible.

Official sources