AQW 12221/22-27 Written question to the Minister of Education

To ask the Minister of Education to detail (i) the schools in East Antrim awaiting the completion of capital projects; (ii) the progress, status, and anticipated completion dates of these projects; and (iii) the current prioritisation ranking of these projects.

Asked by Stewart Dickson MLA on 20 May 2024

  • Answered
  • Written
Tabled
20 May 2024
Answer due by
5 June 2024
Answered
29 May 20249 days after tabling
Department
Department of Education
Priority question
No

Answer

There are currently seven capital projects in East Antrim awaiting completion.

The current position of these projects is as follows:

SchoolCurrent Position
Islandmagee Primary SchoolProject is in the construction stage, with completion anticipated in summer 2024.
St Killian’s CollegeProject is in the design stage and a revised planning application is to be submitted in the coming months.
Belfast High SchoolThe project was announced in March 2022, however was paused in April 2023.
Carrickfergus AcademyProcurement of an Integrated Consultant Team for the project has commenced, following the re-start of the project in February 2024.
Larne Grammar SchoolThe project was announced in March 2022, however was paused in April 2023.
Larne High SchoolThe project was announced in March 2022, however was paused in April 2023.
Ulidia Integrated CollegeProject is in the construction stage with completion anticipated by the end of 2024.

Projects will continue to advance in planning and design but will only be permitted to progress to construction when affordable within the wider education budget context. As I have previously stated, it is my intention to continue to make the case for significant additional and sustained capital budget to invest right across the schools’ estate.

Official sources