AQW 26072/11-15 Written question to the Minister for Regional Development

To ask the Minister for Regional Development to detail the number of passengers using the Larne Railway Line since the introduction of the 2013 timetable compared to the comparable period under the previous timetable.

Asked by Stewart Dickson MLA on 20 September 2013

  • Answered
  • Written
Tabled
20 September 2013
Answer due by
7 October 2013
Answered
2 October 201312 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

The current railway timetable on the Larne line commenced on 24 March 2013. Translink advise 1,008,075 passenger journeys have been recorded on the Larne line from April to September 2013 compared to 849,243 in the corresponding period in 2012.