AQW 26073/11-15 Written question to the Minister for Regional Development

To ask the Minister for Regional Development when six-carriage trains will be fully deployed on the Larne Railway Line.

Asked by Stewart Dickson MLA on 20 September 2013

  • Answered
  • Written
Tabled
20 September 2013
Answer due by
7 October 2013
Answered
2 October 201312 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

At present NI Railways regularly operate one 6-carriage train during both the morning and evening peaks on the Larne Line.

Deployment of 6-carriage trains is based on need across the network and NI Railways continue to monitor passenger loadings on all peak services.